Projects

5

Active Projects

£165,715.00

Active Project Value

£58,385.556

Active Invoiced

£58,385.556

Outstanding Balance

Active filters: Sorted by: customer_name (A-Z)

149 Projects

J0004Active

General Vehicle expenses

Value:£0.00
Progress:0%
J2843Completed

ADS Ltd

Sub Contract Labour @ MCR Factory Sat & Sun

Value:£2,269.00
Progress:100%
J2791Completed

ADS Ltd

Manchester Factory - North and south Stair

Value:£35,441.00
Progress:100%
J3017Completed

ADS Ltd

Tech Support - E1 Unit/MIMIC Panel - Hove Gardens

Value:£400.00
Progress:100%
J3179Completed

ADS Ltd

Brighton Hove Gardens Call Out

Value:£1,107.50
Progress:100%
J2737Completed

ADS Ltd

Chatfield Road Controls

Value:£37,087.00
Progress:100%
J3059Completed

ADS Ltd

Repair Failed PSU at The Square Birmingham

Value:£1,732.00
Progress:100%
J2845Completed

ADS Ltd

2x Electrical Engineers MCR Factory 4th-7th July

Value:£7,750.00
Progress:100%
J2836Completed

ADS Ltd

Control Panels Block A & Block B

Value:£83,650.00
Progress:100%
J2832Completed

ADS Ltd

2x Install Engineers for Manchester Factory

Value:£3,036.00
Progress:100%
J2879Completed

ADS Ltd

Dual supply auto changeover modification

Value:£2,345.00
Progress:100%
J2746Completed

ADS Ltd

Hove Garden Control

Value:£44,428.00
Progress:100%
J3164Completed

ADS Ltd

Investigate Non-Functioning Mimic Panel

Value:£1,325.00
Progress:100%
J2818Completed

ADS Ltd

Mimic Panels IP54, Manchester Factory North, South & Theatre

Value:£10,314.00
Progress:100%
J2844Completed

ADS Ltd

PLC Software Engineer and 2off Electrical Engineers

Value:£8,551.00
Progress:100%
J3053Completed

ADS Ltd

Supply of Replacement HMI for Block B Hove System

Value:£3,099.86
Progress:100%
J2839Completed

ADS Ltd

Chatsfield Road Mods

Value:£5,992.00
Progress:100%
J2810Completed

ADS Ltd

Manchester Factory - Theatre

Value:£16,895.00
Progress:100%
J2837Completed

ADS Ltd

2 x Install Engineers MCR Factory 6th & 7th June

Value:£3,344.00
Progress:100%
J2831Completed

ADS Ltd

Control & Mimic Panel Acceleration

Value:£7,800.00
Progress:100%
J2801Completed

ADS Ltd

ATS PANELS - BUILD AND SUPPLY OF 4 OFF AUTO TRANSFER SWITCH PANELS

Value:£12,110.00
Progress:100%
J2664Completed

AESC UK Ltd

Decant gripper modifications

Value:£1,745.00
Progress:100%
J2963Completed

AESC UK Ltd

Control Systems OPC Master

Value:£154,091.00
Progress:100%
J3004Completed

AESC UK Ltd

Control Panel Snag Rectification Works

Value:£10,000.00
Progress:100%
J2498Completed

AESC UK Ltd

Envision - Packing Gripper

Value:£221,758.00
Progress:100%
J2703Completed

AESC UK Ltd

Engineering Day Rate

Value:£1,300.00
Progress:100%
J2716Completed

AESC UK Ltd

Envision Spare Conveyor Parts

Value:£594.00
Progress:100%
J3070Completed

AESC UK Ltd

Supply 3 off Rack Mounted Power Supplies

Value:£554.60
Progress:100%
J3038Completed

AESC UK Ltd

Supply of Siemens Equipment

Value:£12,590.00
Progress:100%
J2524Completed

AESC UK Ltd

Universal Stack 60kw Manual Transfer

Value:£15,987.00
Progress:100%
J2668Completed

AESC UK Ltd

Fanuc commissioning support

Value:£3,000.00
Progress:100%
J2497Completed

AESC UK Ltd

Envision - Decant Robot cell

Value:£221,758.00
Progress:100%
J2523Completed

AESC UK Ltd

Universal Stack Manual Transfer

Value:£4,094.00
Progress:100%
J2645Completed

AESC UK Ltd

Decant stillage location modifications

Value:£4,000.00
Progress:100%
J2740Completed

AESC UK Ltd

Scissor Lift repair and Pec's

Value:£2,735.00
Progress:100%
J2496Completed

AESC UK Ltd

Envision - 398 Robot cell

Value:£277,486.65
Progress:100%
J3082Completed

AESC UK Plant 2 Limited

Injection Line 1 Handy Panel Install

Value:£18,750.00
Progress:100%
J3157Completed

AESC UK Plant 2 Limited

TabLam Safety Mods L1- Add cost to go with 4800108853

Value:£2,440.75
Progress:100%
Due Date:17/03/2026
J3155Completed

AESC UK Plant 2 Limited

Tab Lam Safety Modification Line 1

Value:£22,325.25
Progress:100%
J3086Completed

AESC UK Plant 2 Limited

Injection line 2 Handy Panel install

Value:£18,750.00
Progress:100%
J2921Completed

AMB

Vacuum Divert Electrical Install

Value:£1,309.00
Progress:100%
J2922Completed

AMB

Lamp Box Installation

Value:£1,591.00
Progress:100%
J2952Completed

AMB

Lamp Box Installation No.2

Value:£1,591.00
Progress:100%
J2753Completed

AR Controls Ltd

AR AGV Lite MK2

Value:£0.00
Progress:100%
J2694Completed

AR Controls Ltd

AR Lite AGV

Value:£0.00
Progress:100%
J2883Cancelled

AR Controls Ltd

CANCELLED

Value:£0.00
Progress:0%
J2392Completed

AR Controls Ltd

AGV Manufacture

Value:£0.00
Progress:100%
J3126Completed

Adler Pelzer Washington Ltd

Stop testing on Contact oven Light guards

Value:£900.00
Progress:100%
Due Date:31/01/2026
J2930Completed

Ashford Orthodontics

Supply of Inverter for Extraction Fan Control

Value:£2,193.00
Progress:100%
J2900Completed

BAE Systems Global Combat Systems Munitions Ltd

Bond Bench Solution - Supply, Install & Commission

Value:£144,885.00
Progress:100%
J3075Active

BAE Systems Land (UK)

BAE Load End Modifications

Value:£23,351.00
Progress:35%
Due Date:31/01/2026
J2965Completed

BBS Switchgear Ltd

PLC & HMI Replacement

Value:£16,812.00
Progress:100%
J2578Completed

Blue Hydraulics Ltd

Nissan Castings Siif HPU wiring

Value:£2,390.00
Progress:100%
J2677Completed

Bourbon Automotive Plastics Ltd

Remote software mods for assy / test benches

Value:£1,680.00
Progress:100%
J2699Completed

Bourbon Automotive Plastics Ltd

LCM201-200N mini strain gauge with cable

Value:£658.75
Progress:100%
J2463Completed

Bourbon Automotive Plastics Ltd

L460/L461 Sliding Lid Assembly Project

Value:£30,787.36
Progress:100%
J2611Completed

Bourbon Automotive Plastics Ltd

Ewon units supply and configuration

Value:£1,032.00
Progress:100%
J2547Completed

Bourbon Automotive Plastics Ltd

Rev1 - solution using colour sensors

Value:£3,900.00
Progress:100%
J2914Completed

Bourbon Automotive Plastics Ltd

Replacement LCM201-100N Strain Gauge

Value:£822.00
Progress:100%
J2522